Renewable Energy · Vestas

Myrnenska Wind Farm – Vestas V150 Installation & Wind Farm Logistics Optimisation

Supporting the construction of Ukraine's largest wind farm through innovative logistics, multi-crane operations and the installation of Vestas V150 4.2 MW wind turbines.

Myrnenska Wind Farm – Vestas V150 Installation & Wind Farm Logistics Optimisation
Client
Vestas
Location
Myrne, Ukraine
Sector
Renewable Energy
Scope
Wind turbine installation · Logistics optimisation · Pre-assembly operations · 18 of 39 turbines installed
Equipment
2 × Liebherr LR1600 (600 t)
1 × Liebherr LR1250 (250 t)
1 × Liebherr LR1160 (160 t)
1 × Liebherr LTM1220 (220 t)
1 × Grove GMK6300 (300 t)
2 × Telehandlers
Result
18 Vestas V150 turbines installed, supporting the successful delivery of Ukraine's largest wind farm at the time.

Optimising Wind Farm Construction Through Innovative Logistics

The Myrnenska Wind Farm was the largest and most powerful wind energy project in Ukraine in 2019, comprising 39 Vestas V150 wind turbines, each rated at 4.2 MW with a 105-metre hub height. Phenyx Rebuild was responsible for installing 18 turbines, delivering the heavy lifting and site logistics necessary to maintain an ambitious construction programme.

Beyond lifting operations, the project introduced new logistics concepts that significantly improved installation efficiency and set a new benchmark for wind farm construction in Ukraine.

Pre-Assembly Logistics Driving Installation Efficiency

Pre-Assembly Logistics Driving Installation Efficiency

For the first time on one of the company’s wind energy projects, a dedicated laydown and pre-assembly area was established to optimise construction sequencing. Components arriving on site were unloaded and prepared using Liebherr LR1160 and LR1250 crawler cranes, allowing nacelles and drivetrains to be assembled before transport to the installation locations. Final erection was performed by two 600-tonne Liebherr LR1600 crawler cranes, enabling continuous installation activities across the site. This coordinated logistics strategy significantly reduced downtime between lifts and contributed to the completion of all 39 wind turbines within approximately four months, with Phenyx Rebuild successfully installing 18 turbines.

Developed an innovative pre-assembly logistics strategy and installed 18 Vestas V150 wind turbines, contributing to the successful delivery of Ukraine's largest wind farm in 2019.