Working inside an existing steel production facility required a lifting solution capable of delivering exceptional precision where conventional cranes could not operate efficiently. Using an SBL1100 hydraulic gantry system, our engineers safely lifted, positioned, and aligned each component within strict installation tolerances. After completing the drive motor installation, the gantry system was relocated to another section of the mill to install the four 90-tonne stands, creating the structural platform for the subsequent installation of the 640-tonne Roughing Mill. The project demonstrated meticulous planning, controlled execution, and the precision engineering required for complex steel plant modernisation.